QUESTION 1
Assumptions are factors that, for PMI pmi-001 pdf planning purposes, are considered to be ______.
A. True, real, or certain
B. True, real, or uncertain
C. Real
D. Verbal
Correct Answer: A
Explanation:
PMBOK describes assumptions as “factors that, for planning purposes, are considered to be true, real, or certain.”

pmi-001

QUESTION 2
Which one of the following comes first in the pmi-001 project plan?
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Correct Answer: A
Explanation:
Scope statement comes first in the project plan. Scope statement is the pmi-001 exam written statement of project. It contains: Project objectives, Project justification, Project deliverables.